ANALISIS PENGARUH KETERLAMBATAN PENYELESAIAN PROYEK KONSTRUKSI DENGAN MENGGUNAKAN METODE EARNED VALUE
STUDI KASUS: PROYEK PENAMBAHAN GEDUNG LANTAI DUA UNIVERSITAS TOMPOTIKA LUWUK
https://doi.org/10.55114/siparstika.v4i2.919
Keywords:
Construction Project, Delay, Earned ValueAbstract
Construction Project is an activity carried out with limited time and resources to achieve the specified end result. In the implementation of a Construction Project, delays often occur where the actual progress of the realization obtained does not match the planned progress. So that it can affect the costs that have been budgeted. This research was conducted at Tompotika University Luwuk Banggai Jl. Dewi Sartika No. 67 Kelurahan Luwuk, Banggai Regency, Central Sulawesi Province. This study aims to determine the factors that cause delays in the project, as well as the impact of the influence of delays on costs in the Addition of the Second Floor Building Project of Tompotika University Luwuk Banggai. The method used in this study is descriptive quantitative, with the analysis tool used is Earned Value (EV) or Result Value.
The results of the study indicate that the main factors causing delays in the Second Floor Building Addition Project of Tompotika University Luwuk Banggai are the implementation of the planned project scheduling is not good, so that the weight of the work realization in the field is not able to reach the weight of the work that has been planned. After conducting an analysis using the Earned Value (EV) method, in the calculation of basic indicators, as well as the calculation of the combination of variance values and performance indexes, it was found that the Second Floor Building Addition Project of Tompotika University Luwuk Banggai, incurred more wasteful actual costs (Over Cost) in the 1st week, which was Rp 17,714,858.82 from the realized cost of Rp 17,699,315.67 with a difference = -15,507.15. However, in the 2nd week to the 16th week, the costs incurred were more economical, namely Rp1,949,701,273.09 from the realization cost of Rp1,957,340,068.05 with a difference = 7,638,794.69. Meanwhile, the project schedule experienced a total delay from week 1 to week 16.
Downloads
References
A Husen (2011), Manajemen Proyek Perencanaan, Penjadwalan dan Pengendalian Proyek, Andi Yogyakarta
A.A Gde Agung Yana (2009), Dalam Skripsi Universitas Atma Jaya Yogyakarta F. Tjusanto, 2013. Faktor Penentu Agar Suatu Proyek Konstruksi Dapat Berjalan Dengan Sukses.
A Imam Utama (2021), Analisis Keterlambatan Proyek Rehabilitasi Jaringan Irigasi Di Lanca Kab. Bone.
Bayu Adi Nugroho (2012), Analisis Faktor Keterlambatan Proyek Terhadap Pembengkakan Biaya Proyek Bangunan Gedung Di Surakarta.
BPS. (2021). Kecamatan Luwuk Dalam Angka. Luwuk.
Chandra Yono Dan Riswanto Wahyudi (2006), Faktor-Faktor Yang Menyebabkan Keterlambatan Suatu Proyek.
Charoenngam & Sriprasert (2001), Pengendalian Biaya Proyek.
Fadhol Yudhagama (2020), Analisis Keterlambatan Proyek Pada Pembangunan Gedung Perpustakaan Uin Sunan Ampel Surabaya.
F Rachim (2022), Manajemen Proyek Perencanaan-Penjadwalan-Pengendalian Proyek, Fakultas Teknik Universitas Fajar.
H Susanto & H Makmur (2013), Auditing Proyek-Proyek Konstruksi, Andi Yogyakarta
Iman Soeharto (1999), Manajemen Proyek, Konseptual Sampai Oprasional, Jakarta, Erlangga, 1999.
Keputusan Presiden (Kepres) No. 61 Tahun 2004. Tentang Pedoman Pelaksanaan Pengadaan Barang/Jasa Pemerintah
Peraturan Presiden (Perpres) No 4 Tahun 2015 Tentang Perubahan Keempat Atas Peraturan Presiden Nomor 54 Tahun 2010 Tentang Pengadaan Barang/Jasa Pemerintah.
Kerzner (2009), Dalam Jurnal Sipil Statik, Deane R. O. Walangitan, Pingkan A. K. Pratasis. Definisi Proyek Konstruksi.
Kraiem Dan Dickman, (1987), Keterlambatan Proyek Yang Dapat Dibagi Menjadi Tiga Jenis Utama : Compensable, Excusable, Non Excusable.
PMBOK (2021), A Guide Project Management Body Of Knowledge. Ketetapan Nialai Earned Value.
PMBOK (2004), Dalam Jurnal Ilmiah Teknik Sipil, Dewa Ketut Sudarsana. Grafik Konsep Nilai Hasil Dalam Bentuk Kurva “S”
Soedrajat (1984), Analisa Rencana Anggaran Biaya.
WI Ervianto (2005), Manajemen Proyek Konstruksi Edisi Revisi.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 putu suartana, Sri Susilawati; Komang Okayana

This work is licensed under a Creative Commons Attribution 4.0 International License.